County Sanitation District No. 3 of Los Angeles upgraded their Marina Pumping Plant. DPSI was hired as the prime contractor to perform the pump replacement work at Pumping Plant No. 3 in Long Beach, California.
DPSI’s scope of work included:
- Demolition of two existing dry pit submersible pumps and associated piping
- Modification of existing piping and valves
- Construction of concrete pump pedestals
- Installation of two 85 horsepower dry pit submersible pumps
- All associated mechanical, structural, and electrical work, and all other appurtenant work